Timeline

2018

October

Complete Montrose-Nucla segment construction
 

2017

September

Begin Montrose-Nucla segment construction
 

August

Complete Montrose-Nucla right-of-way improvements
 

May 31

End Phase II construction of the 345kV Montrose Substation
 

Tri-State elects board officers at 65th Annual Meeting

April 6, 2017

Tri-State Generation and Transmission Association held its 65th Annual Meeting on April 5 in Broomfield, Colorado, with over 425 electric cooperative representatives and industry officials in attendance. Tri-State is the cooperative wholesale power supplier to 43 member electric distribution cooperatives and public power districts in Colorado, Nebraska, New Mexico and Wyoming.